
See How We Deliver
From design through delivery, engineering the systems that support heavy industries and utilities since 1969.
Heavy Industrial
Large Terminal Expansion
Oil and Gas
Large Terminal Expansion
Oil and Gas
Scope of Work
- Increase tank storage and distribution at the existing terminal
- Project added twelve 150,000 BBL storage tanks, one 15,000 BBL transmix tank, six transfer pumps with a combined maximum capacity of 55,000 BPH, one blending pump and two stripping pumps
- Orbital executed multi-discipline engineering for all disciplines including subcontract of geotechnical services and stormwater management with trusted partners
- Orbital supported procurement activities through bid reviews, technical bid evaluations and vendor recommendations, vendor document review and delivery expediting
Deliverables
- Process design basis, PFDs and P&IDs
- Material requisition packages for tanks and pumps
- Revised site plan incorporating changes for storm water runoff and drainage, fencing and landscaping
- Navisworks model, general arrangement drawings, piping plans and isometrics
- Foundation and steel drawings for supporting the new tanks, pumps, piping and electrical infrastructure
- Civil design deliverables for 200’x50’x25’ deep outbound manifold pit, 175’x50’ inbound wing manifold and grading / paving modifications at the terminal
- Single line diagrams, power plans, duct bank and cable tray plans, lighting plans, grounding plans, cable & conduit schedules, panelboard schedules
- Instrument location plans, wiring diagrams, loop diagrams, instrument datasheets
- Scope of work documents for demolition and installation
Project Highlights
- Expansion increased the Terminal ability to handle external demands for multiple product grades and larger volumes as well as supported internal stakeholder desires for greater flexibility in meeting seasonal demand and market fluctuations.
- Total Installed Cost (TIC) – $200MM
More Projects
Featured
Natural Gas Processing
Natural Gas
Heavy Industrial
Feed Impurity Removal
Specialty Chemical
Heavy Industrial
Reactor Heating Process Improvement
Specialty Chemical
Asset Management
Asset Management Program for a Steel Mill Client
Steel
Asset Management
OH-Crane, Crane Runway and Building Inspection
Steel
Asset Management
Bridge Inspection and Turnkey Repairs
Power Generation
Utilities
Department Of Transportation (DOT) Project
Electric Distribution Engineering
Department Of Transportation (DOT) Project
Electric Distribution Engineering
Scope of Work
- Construction design for the relocation of existing 25kV sub-transmission and 15kV distribution overhead utilities to accommodate Department of Transportation (DOT) highway modifications and widening
- Coordinated with Department of Transportation (DOT) and other utilities for phased construction approach
- Facilitated and obtained private right of ways for new utility structures and easements
- Completed forestry efforts
- Designed demolition of existing facilities and distribution equipment
- Provided engineering support for highway rated underground utility designs
Deliverables
- Site visits to scope and assess constructability of relocations
- Produce a detailed design and construction package (cost estimate, design sheets, design maps, bill of material, circuit diagram, and material reservation using client work management application)
- Coordinate easement and permit research and secure permits with local and state jurisdiction
- Create and distribute construction packets
- Provide design support during construction
Project Highlights
- Orbital upheld all Department of Transportation (DOT) cost and schedule commitments throughout this multi-year effort, which began prior to 2020 and continued through COVID-era restrictions. When the utility partner faced internal resource limitations, Orbital stepped in to provide critical design and engineering support, keeping the project on track and maintaining construction momentum.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
New 69kv-12.5kv Substation
Substation Engineering
New 69kv-12.5kv Substation
Substation Engineering
Overview
- Location: Indiana
- Client: Midwest Investor-Owned Utility
- Timeline: Approximately 9 months
Scope
- Design civil and drainage plan for new substation
- Design new 69kv-12.5kv substation including the following major pieces of equipment:
- (2) 69kv incoming line load break disconnect switches
- (2) 69kv bus tie disconnect switches
- (2) 69kv circuit switchers for primary transformer protection
- (2) 69kv-12.5kv, 28mva transformers
- (1) 12.5kv switchgear building with (5) 12.5kv feeder circuits
- Design 12.5kv feeder cable/conduit runs to 1st pole outside of the substation
- Perform grounding study and design ground grid
- Prepare storm water pollution prevention plan (SWPPP) for project
View More Projects
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Asset Management
Bridge Inspection and Turnkey Repairs
Power Generation
Bridge Inspection and Turnkey Repairs
Power Generation
Scope of Work:
- Performed a comprehensive inspection of a ~1,000-foot suspension bridge spanning a major waterway
- Utilized ground-based, elevated walkway, and rope-access techniques to evaluate hard-to-reach areas
- Benchmarked findings against prior inspection reports to identify changes and new deficiencies
- Classified deficiencies by priority level to guide repair urgency and scope
- Performed engineering analysis and developed Standard Repair Procedures (SRPs) for identified deficiencies
- Coordinated access constraints, including railroad scheduling, live powerline limitations, and follow-up inspections
- Executed turnkey repair construction for the north half of the bridge, including demolition and repairs
- Provided construction coordination, safety planning, and on-site quality oversight
Deliverables:
- Phased inspection reports as segments of the bridge were completed
- A repair prioritization ranking assigned to each finding
- Standard Repair Procedures (SRPs) and engineering repair IFC drawings for Priority 1 deficiencies
- Construction coordination and quality assurance documentation
- Final inspection report and repair verification records
Project Highlights:
- Orbital delivered a comprehensive inspection and turnkey repair program for a 1,000-foot suspension bridge, combining rope-access inspection, structural engineering, and construction oversight to address complex access and safety challenges. The inspection identified 43 deficiencies, including multiple Priority 1 conditions such as widespread cracked welds, severe section loss in a primary truss chord, and extensive concrete spalling with exposed reinforcement. Orbital executed phased reporting to support timely decision-making and completed full demolition and repairs on the north half of the bridge. When lead-containing coatings were discovered mid-demolition, Orbital paused work, coordinated with regulatory agencies, and implemented a revised, compliant construction plan – allowing repairs to resume and conclude efficiently while maintaining safety, regulatory compliance, and structural integrity.
More Projects
Featured
Natural Gas Processing
Natural Gas
Heavy Industrial
Feed Impurity Removal
Specialty Chemical
Heavy Industrial
Reactor Heating Process Improvement
Specialty Chemical
Asset Management
Asset Management Program for a Steel Mill Client
Steel
Asset Management
OH-Crane, Crane Runway and Building Inspection
Steel
Asset Management
API 653 Tank Inspection and Floor Replacement
Specialty Chemical
Utilities
Buried Regulator Program Evaluation
Natural Gas
Buried Regulator Program Evaluation
Natural Gas
Scope of Work
- Evaluated 3,300 buried gas regulators across a regional network
- Developed cost-efficient remediation strategies based on risk and infrastructure proximity
- Assessed replacement options, including mainline extensions and above-grade designs
- Benchmarked project costs using historical construction data
- Built geospatial tools to identify regional clusters and prioritize replacements
- Created installation guidelines using a data-driven breakeven distance threshold
Deliverables
- Engineering assessment report including:
- Cost comparisons for above-grade vs. below-grade remediation methods
- Risk evaluation and compliance considerations
- Capital project analysis of 27 replacement efforts
- GIS-based proximity analysis and cluster modeling to guide future planning
- Prioritization tool using spreadsheet, dashboard, and geospatial integration
- Replacement decision-making framework incorporating breakeven cost thresholds
- Tracking enhancements to align asset records across engineering and mapping systems
Project Highlights
- The project produced a utility-wide remediation model for buried gas regulators, defining per-regulator cost drivers and a breakeven point for choosing between regulator replacement and main extensions. Orbital analyzed multiple design alternatives to standardize future installations and enable strategic, program-wide planning through GIS, engineering analytics, and stakeholder input.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Utilities
Odorant Replacement Project
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Heavy Industrial
Feed Impurity Removal
Specialty Chemical
Feed Impurity Removal
Specialty Chemical
Scope of Work
- The objective of this project was to remove the oil and grease from the incoming feed flow that is utilized throughout the plant’s operations
- With these impurities being removed prior to the feed entering the Strippers, it improved the efficiency of the production at the site
- Project included installation of two oil storage tanks and six pumps with containment with all interconnecting piping, steel and supports
- A raised MCC structure on piles and a concrete pad supported transformer was added to the east of the main project area to supply power for the project and a new Delta V Cabinet with HMI was located in the new MCC building
- The existing truck parking was relocated to the northeast along with connecting existing roadways to allow for a different exit path
- New surveillance cameras were integrated with an existing camera network located at gate to the East of the proposed parking location
- Full electrical scope included adding a 13.8kV feeder, 13.8kV/480V transformer, substation building, 480V motor control center, VFD’s, UPS, panels, control stations, lighting, grounding, and associated cable tray/conduit and cables
Deliverables
- Revised site plan
- Navisworks model, general arrangement drawings, piping plans and isometrics
- Piping, foundation and steel drawings for supporting new tanks, pumps, MCC, transformer and piping
- Grading plans, sections and details for new roadway and parking lot
- Material requisition packages for major electrical equipment – 13.8kV switch, 13.8kV to 480V transformer, substation building, 480V MCC, UPS System
- Single line diagrams, power plans, duct bank and cable tray plans, lighting plans, grounding plans, cable & conduit schedules, area classification drawings
- Instrument location plans, wiring diagrams, loop diagrams, instrument datasheets, control narratives
- Scope of work documents for construction
Project Highlights
- Maintenance work was minimized significantly as a result of the project, decreasing downtime while increasing productivity.
- Total Installed Cost (TIC) – $120MM
More Projects
Featured
Natural Gas Processing
Natural Gas
Heavy Industrial
Reactor Heating Process Improvement
Specialty Chemical
Asset Management
Asset Management Program for a Steel Mill Client
Steel
Asset Management
OH-Crane, Crane Runway and Building Inspection
Steel
Asset Management
Bridge Inspection and Turnkey Repairs
Power Generation
Asset Management
API 653 Tank Inspection and Floor Replacement
Specialty Chemical
Heavy Industrial
Chemical Plant
Specialty Chemical
Chemical Plant
Specialty Chemical
Scope of Work
- Project included the installation of two new reactors into an existing enclosed facility
- Laser scanning was conducted to collect field data for the 10-level existing facility
- One new reactor was tied into the existing DCS system with the other reactor expected to be tied in at a later date
Deliverables
- Navisworks model, general arrangement drawings, piping plans and isometrics
- Steel drawings for supporting the new reactors, piping and conduit
- Instrument location plans, wiring diagrams, loop diagrams, instrument datasheets
- Scope of work documents for construction
Project Highlights
- Laser scan data supported constructability reviews and definition of demolition needed to lower the 2 new reactors through the roof and down to level 3.
- Total Installed Cost (TIC) – $3.2MM
More Projects
Featured
Natural Gas Processing
Natural Gas
Heavy Industrial
Feed Impurity Removal
Specialty Chemical
Heavy Industrial
Reactor Heating Process Improvement
Specialty Chemical
Asset Management
Asset Management Program for a Steel Mill Client
Steel
Asset Management
OH-Crane, Crane Runway and Building Inspection
Steel
Asset Management
Bridge Inspection and Turnkey Repairs
Power Generation
Heavy Industrial
Coal Delivery System Modification
Power Generation
Coal Delivery System Modification
Power Generation
Scope of Work
- Coal fired power generation facility client faced a dilemma with their existing barge unloader only capable of unloading barges up to a specific width, limiting the type of barge that can be used in delivery
- Further complicating the delivery, the barges that fit within the constraints of the unloader are becoming less available due to age
- Orbital developed conceptual solution for a new barge unloading system that allowed for unloading jumbo barges to the existing surge bin via deck mounted Sennebogen cranes, hoppers and conveyors on a new deck barges and incline conveyors to the existing surge bin
- Once approved, Orbital executed detailed design including procurement support in equipment specification and selection, owner’s engineering and construction support
Deliverables
- General arrangement drawings and total installed cost estimates for various solutions
- Material requisition packages for conveyors and hoppers
- Conveyor support steel drawings and foundations
- Single line diagrams, power plans, lighting plans, grounding plans, cable & conduit schedules
- Scope of work documents for construction
Project Highlights
- Project was originally deemed an “unsolvable problem” due to complexities in the design interfaces, contractual interfaces between delivery and client and limited remaining operating window for the facility. Orbital’s efficient solution allowed for the project to be authorized, and the facility is currently conducting coal unloading operations via the new unloading system. The facility operating permit has been extended since project completion making the solution benefits realized well into the future.
- Total Installed Cost (TIC) – $4MM
More Projects
Featured
Natural Gas Processing
Natural Gas
Heavy Industrial
Feed Impurity Removal
Specialty Chemical
Heavy Industrial
Reactor Heating Process Improvement
Specialty Chemical
Asset Management
Asset Management Program for a Steel Mill Client
Steel
Asset Management
OH-Crane, Crane Runway and Building Inspection
Steel
Asset Management
Bridge Inspection and Turnkey Repairs
Power Generation
Utilities
Odorant Replacement Project
Natural Gas
Odorant Replacement Project
Natural Gas
Scope of Work
- Replaced aged odorant injection system, storage tank, containment, and building at gate station
- Decommissioned and remove existing and abandoned odorant systems and associated infrastructure
- Developed and install new odorant system including shelter, piping, controls, foundations, and electrical
- Coordinated full engineering lifecycle: design, demolition, procurement support, construction oversight, and commissioning
- Executed project within defined shut-in window to maintain system reliability and operational continuity
Deliverables
- Redlined piping and instrumentation diagrams, 3D model, isometric piping drawings, construction bill of material, and valve tie-in lists
- Civil, mechanical, structural, and electrical drawings
- Demolition drawing packages with mechanical, electrical, and instrumentation and controls scopes
- Procurement packages for tank, building, odorant system, and temporary odorization
- On-site construction support, contractor coordination, and commissioning oversight
- Final documentation including updated drawings, redlines, and closeout package
Project Highlights
- The project executed a full odorant system replacement within a limited five-month shut-in window, managing the demolition of two systems in parallel with the new installation to maintain site layout. The team proactively coordinated a temporary odorization option in case of commissioning delays, provided continuous oversight from initial design through construction and as-built documentation, and supported the development of long-term record drawings and standardized site files for future reuse.
More Projects
Utilities
138kV Substation Expansion
Substation Engineering
Featured
345k Double Breaker Interconnect Substation
Construction Management
Utilities
Management Programs
Construction Management
Utilities
Inlet/Outlet Valve Evaluation
Natural Gas
Featured
Federal Funded Maintenance Program Management
Natural Gas
Utilities
Utilities and Internet Service Providers
Joint Use Make Ready Engineering
