Transmission Pipeline Detailed Engineering
Transmission Pipeline Detailed Engineering
Orbital performed the detailed design for the replacement of existing 10” and 12” natural gas mains with approximately 3.5 miles of 16” high pressure steel pipeline. Scope of this project included performing survey, Geotech investigation, developing design drawings, construction specifications and equipment and material lists for the pipeline and pigging (launcher and receiver) facilities, cathodic protection design, odorization plan, permitting support, QA/QC requirements, including a TIC estimate.
UAV Inspection
Unmanned Aerial Vehicle (UAV) Inspections combined with Alignment Surveys of Crane Runways Orbital Technical Solutions (OTS) provided Asset Integrity Services with use of Unmanned Aerial Vehicles (UAVs) and survey equipment. The equipment was used to complete visual...